Flushing-a-Fan-Coil-Valve-Package-Article_Header-Image-2_640x360_acf_cropped

DOES BG29/2021 IMPACT ON THE SYSTEM DESIGN & FLUSHING OPERATIONS OF FCU CIRCUITS?

10 May

Evolution of BSRIA Application Guide “Pre-Commissioning Cleaning of Pipework Systems”

System contaminates and debris will inevitably be found in newly fabricated heating and cooling pipework systems. If allowed to remain in the system in sufficient quantity the system will be prone to blockage at the strainers, control valves and the small bore FCU coil. They may also initiate corrosion and encourage the growth of microorganisms.

The subject of cleaning pipework systems to remove contaminants prior to commissioning was first addressed in 1991 in the BSRIA application guide AG8/91 Pre-Commissioning Cleaning of Water Systems. Experience has shown that systems that are designed and cleaned following this guidance are less likely to suffer operating problems. The next two updates AG1/2001 and AG1/2001.1 included feedback from the industry, covered bacteria related issues, Pseudomonas-like bacteria in particular, that had become a common problem in the 90s and an entirely new section dedicated to adding new pipework to an existing system as this process had proven to bear a serious contamination risk.

In 2011 the application guide was renamed BG29/2011 and incorporated more industry feedback as well as roles and responsibilities of, and guidelines for consistent communication between parties involved in system cleaning & flushing. In 2011, the design & flushing process for FCU circuits was still based on a constant flow pump strategy, with a 4-Port valve on the FCU and a DRV in the return. The system was designed for back flushing the FCU, with a flushing bypass installed upstream of the coil, control and regulating valves, to exclude the FCU from chemical cleaning and a drain valve in the flow to the terminal unit facilitating back flushing of the unit.

The next edition BG29/2012 included European and British standards, and for the first time a variable flow pump strategy with PICVs and a 4-Port and Constant Flow Valve on the end-of-line terminal unit, referencing the energy saving potential of variable flow systems, as explained in BG12/2011 “Energy Efficient Pumping Systems”. The recommended back flushing process remained unchanged but problems were anticipated when back-flushing the terminal unit due to the small orifice of the PICV. Therefore a secondary design was included, recommending the installation of a drain valve between coil and PICV enabling forward flushing of the coil at full velocity without the flow passing through the PICV.


BG29/2012 variable flow system design with PICVs & ABV 4-Port, designed for back flushing

BG29/2012 secondary variable flow design designed for forward flushing

However, the 6th edition BG29/2020 published in May 2020 was a major departure from the BG29/2012 version. The system design was optimised for the energy-saving variable flow strategy, completely PICV controlled, including the end of line FCU. In the 2020 design the drain valve in the flow was removed, promoting forward flushing through the FCU as the most effective  flushing method.

BG29/2020 variable flow system design with PICVs, designed for forward flushing

Furthermore, the design was changed from the previously recommended 4 Port/constant flow valve on the end-of-line FCU to fully PICV-controlled. The end-of-line FCU is now designed with a PICV, with an additional PICV with temperature sensors in the return of the branch. The branch PICV only reacts when the sensed temperature in the pipe drops below its setpoint value. This doesn’t impact on flushing the FCU branch other than that the end of line PICV must be isolatable and demountable for flushing.

What changes relevant to FCU flushing were introduced in BG29/2020 and 2021?

The short answer to that question is: None. Our comparison of the latest version BG29/2021 amended 6th edition to the previous one (BG29/2020) shows some minor iterations and slight amendments, which do not affect FCU circuits from a design/valve configuration or flushing perspective.

Why does the flushing direction matter?

The flushing direction as such is not important. The ability to flush the Fan Coil Unit at full velocity however, is extremely important to maintain the water quality in the system. As stated in the opening paragraph, poor water quality can lead to the growth of microorganisms, corrosion and blockage of essential component parts, which ultimately would lead to compromised occupant comfort and higher energy consumption as well as costly maintenance and repairs.

Full velocity can only be achieved when a clear path without constraints is available. The initial back flushing method of the variable flow coil circuit (BG29/2012) contained significant constraints (the flow measurement and PICV). The forward flushing method sees all constraints removed, providing a clear path for the water to achieve full velocity.

How does the BG29 Application Guide impact on the fan coil valve package?

FloControl Ltd. has supplied the UK building services market for over 10 years with valve set assemblies for FCU circuits. FloControl works closely with Fan Coil Unit manufacturers as well as ME consultants, contractors and commissioning engineers. Taking into consideration the experience gained over the past 10 years as well as the recommendations from the BG29 Application Guide, we believe that the key points for a successful fan coil valve package are:

  1. A clear path for flushing the system and terminal unit at the full recommended flushing velocity.
  2. Flexibility to forward and back flush.
  3. Ability to isolate the FCU.
  4. Flexibility to drain the flow and/or return connection of the FCU.
  5. Ability to fill and vent at the FCU.
  6. Versatility to cope with a multitude of FCU designs.

Let’s run through these key points in detail.

1. A clear path for flushing at full velocity

Fan coil unit valve configuration requirements may vary by FCU manufacturer or project, taking into account specific conditions such as limited space. While the BG29 compliant configuration allows for a clear path to forward flush the FCU at high velocity, we also see in the market a slightly more compact configuration, featuring the metering station in the flow, which will restrict the flushing velocity. This approach is widely practiced in the UK without any recorded adverse impact on the coil  or energy consumption.

System Flush

Tip for system flush:

When using a flushing bypass it is essential that the bypass has a full bore large enough to accommodate system flushing velocities.

FCU Flush

BG29 compliant FCU flush

Widely used Compact Configuration forward flush (constrained)

Compact Configuration with blank cap back flush clear path

Tip for FCU flush:

If you want to use the most compact fan coil unit valve set it is recommended to choose a PICV with removable insert. During FCU flushing the PICV insert can be replaced with a blank cap, clearing the path for a full velocity FCU flush.

2. Flexibility to forward and backward flush

The PICV should never be back-flushed at flushing velocity. However, to clear the water between the bypass and the PICV in the return branch, the bypass back drain option remains necessary.

BG29 compliant

3. Ability to isolate the FCU

The BG29/20 & 21 designs recommend 3 isolating valves to achieve maximum flexibility to bypass, isolate, back or forward flush the coil or allow for full flow. This is not practical when fitting a fan coil unit valve arrangement directly onto a FCU with the flow and return pipework on 40mm centres. A special bypass valve incorporating two 3-way ball valves is recommended.

4. Flexibility to drain the flow and/or return connection of the FCU

While the BG29/20 and 21 schematic for FCUs doesn’t show a drain in the flow any longer, we recommend installing a Drain and PT Plug, which is available as a dual-function in component. In a vertically configured valve assembly the drain can be useful to drain the FCU through the low positioned drain rather than opening a union connection. A more complete, less messy solution at a negligible incremental cost!

5. Ability to vent at the FCU

BG29/20 & 21 as well as the previous application guidelines are consistently recommending to include air vents at high points to release air during system filling. When the FCUs are located at the highest point, it is advisable to consider an air vent on each coil. We are recommending inclusion of either a union drain valve, which is useful for filling the system and venting or an automatic air vent for automatic venting at the high point of the flushing bypass.

    

6. Versatility to cope with a multitude of FCU designs

Besides BG29, there are other factors to consider when selecting an FCU Valve assembly.
Union connections on all joints allow for easy valve and components alignment and removal.
Horizontal & vertical alignment options to cope with OEM’s requirements.
A compact design that fits over the FCU drip tray to avoid incremental cost for insulation.
Consider the use of a PICV with removable insert. This may be useful for flushing the return connection on the FCU. The removable insert can be replaced with a blank cap during flushing operations and will be returned afterwards. It will certainly be helpful for flushing the branch when using a PICV as end-of-line solution as the insert can simply be removed instead of the entire valve.

While BG29/2021 hasn’t impacted on the system design and flushing operations of FCU circuits, its predecessor BG29/20 has influenced the industry standard. By ensuring we keep the system as clean as possible through high velocity flushing operations, a contribution will be made to reduce the energy use of the installation and to lower the maintenance costs.

Queries? Contact us [email protected]

Header Image Credit: https://https://www.safewater.org/operation-water-flow-1/2017/2/19/how-is-my-water-purifed-grades-8-12

download